KDOT PMS Replacement Project

R-PMS System Use Cases : Model . KDOT-PMS Use Cases by Date : Pool

Task - T11-02 1R Projects out to PPDC/Chief C&M/DCs link

Properties
Name Value
Description

Send project candidate lists out to the PPDC/Chief C&M/DC's

Transit From
Name
 Allow for economic assumption flexibility : Requirement
 Use or replace CRF web app to get project "actuals" from field personnel : Requirement
 Project Management Systems Integration : Requirement
 Interface or ingest current data for project tracking for Pavement Management purposes : Requirement
 Interface or ingest current data about current or scheduled pavement surfacing projects - PROJECT : Requirement
Transit To
Name
 T11-02 1R Projects out to PPDC/Chief C&M/DCs : Use Case
Id BP220.BP318
Start Quantity 1
Completion Quantity 1
Suppress Join Failure false
Enable Instance Compensation false
Process Type None
Status None
Compensation false

Task Type
Name Value
Name Rule
Implementation
Name Value
Name Implementation

Relationships Summary
Name Begin End
  : Sequence Flow
 T11-02 1R Projects out to PPDC/Chief C&M/DCs : Task
 T12-01 Non-state HPMS Samples received from Planning : Task
  : Sequence Flow
 T11-01 Clean up data collection continued : Task
 T11-02 1R Projects out to PPDC/Chief C&M/DCs : Task

Relationships Detail
Name Value
Name
From
 T11-02 1R Projects out to PPDC/Chief C&M/DCs : Task
To
 T12-01 Non-state HPMS Samples received from Planning : Task
Id BP220.BP321
Condition Type None
Immediate Unspecified
Quantity 1
Timeout 0

Name Value
Name
From
 T11-01 Clean up data collection continued : Task
To
 T11-02 1R Projects out to PPDC/Chief C&M/DCs : Task
Id BP220.BP319
Condition Type None
Immediate Unspecified
Quantity 1
Timeout 0

Appears In
Diagram
 R-PMS System - KDOT-PMS Business Processes by Date : Business Process Diagram
KDOT PMS Replacement Project