KDOT PMS Replacement Project

R-PMS Requirements : Package . Project Management Systems Integration : Requirement

Requirement - Use or replace CRF web app to get project "actuals" from field personnel link

Properties
Name Value
Description

The solution shall preserve the existing functionality of the interface between the Completed Rehab Form (CRF) web app and the PMS. This interface passes data from the CRF web app to PMS and helps track which projects are expected for completion in the calendar year and then to get the actual location, scope, open to unrestricted traffic date, mix, layer thickness rumble strip, and shoulder information about the project into the system.

Transit To
Name
 T01-01 Gather Data to Allow Collection : Task
 T09-01 Track completed and planned projects : Task
 T11-02 1R Projects out to PPDC/Chief C&M/DCs : Task
 Complete Rehab Form (CRF) : Task
Id R-PMS 10.2
Stereotypes PM Integration

Attributes
Name Type Value
Text Text
ID Text R-PMS 10.2
Source Text
Kind Ad Hoc Enumeration Functional
Model Model Element
Risk Ad Hoc Enumeration High
Verify Method Ad Hoc Enumeration Test
ReqType Ad Hoc Enumeration M-Mandatory

Appears In
Diagram
 R-PMS System - Master Requirements for KDOT Replacement PMS System : Requirement Diagram