Task - T06-03 Finish loading Joint Distress data into PMS link

Properties
Name Value
Description

This step involves the loading of the 1/200th mile segment data aggregate / metadata regarding IRI, rutting, faulting, and TCR indices

Transit From
Name
 Interface or ingest historic pavement Joint Distress Collection data : Requirement
 Pavement Condition Collection Systems and Data Integration : Requirement
Transit To
Name
 T06-03 Finish loading Joint Distress data into PMS : Use Case
Id BP220.BP256
Start Quantity 1
Completion Quantity 1
Suppress Join Failure false
Enable Instance Compensation false
Process Type None
Status None
Compensation false

Task Type
Name Value
Name Rule
Implementation
Name Value
Name Implementation

Relationships Summary
Name Begin End
  : Sequence Flow
 T06-03 Finish loading Joint Distress data into PMS : Task
 T06-04 Continue loading LCMS data : Task
  : Sequence Flow
 T06-02 Calculate Road Categories : Task
 T06-03 Finish loading Joint Distress data into PMS : Task

Relationships Detail
Name Value
Name
From
 T06-03 Finish loading Joint Distress data into PMS : Task
To
 T06-04 Continue loading LCMS data : Task
Id BP220.BP259
Condition Type None
Immediate Unspecified
Quantity 1
Timeout 0

Name Value
Name
From
 T06-02 Calculate Road Categories : Task
To
 T06-03 Finish loading Joint Distress data into PMS : Task
Id BP220.BP257
Condition Type None
Immediate Unspecified
Quantity 1
Timeout 0

Appears In
Diagram
 R-PMS System - KDOT-PMS Business Processes by Date : Business Process Diagram
KDOT PMS Replacement Project